US energy regulator unveils new plan to speed up grid-connection for renewables

EN
Add to Favorites

The US Federal Energy Regulatory Commission (FERC) last week issued a proposed rule to accelerate the connecting of new renewable energy generators to the grid and alleviate the enormous backlog in interconnection queues.

At the end of 2021, more than 1,400 GW of renewable energy generation and storage projects were delayed in interconnection queues across the US, with facilities now needing to wait an average of more than three years to connect to the grid, according to the regulator.

Many grid operators and utilities have been employing the “first-come, first-served” processes, which have few safeguards to weed out speculative interconnection requests. Some of them are thus shifting to “first-ready, first-served” processes, which would put more burdens on project developers to demonstrate that the projects are likely to be completed as planned. 

Don't fall behind the market
Carbon prices, CBAM rules and energy policy shift weekly. Subscribe to unlock this article and all of RECCESSARY's market intelligence.
MONTHLY
US$9.90 /mo
Full flexibility — cancel anytime
Subscribe monthly
BEST VALUE · SAVE US$19.80
ANNUAL
US$8.25 /mo US$9.90
US$99 billed annually · 2 months free
Start your 14-day free trial
Unlimited article access Green power & carbon price data Members-only newsletter Report downloads
New readers enjoy a 14-day free trial · Already a member?
IATA launches online tool to help travelers calculate flight emissions
US, EU launch new global initiative to cut methane emissions
Back

More Related News

TOP
Download request

Please fill out the form to download samples.

Name
Company
Job title
Company email
By using this site, you agree with our use of cookies.